Herceg Novi

Implemented projects

Water Supply and Sanitation Adriatic Coast – Herceg Novi
PHASE III (construction of water supply and sewerage infrastructure)
Project status: Completed
Value: € 21,376,171.52 (final contract price)
Funding sources: KfW loan €17.898 mil, own contribution of the GoM €2.923 mil., Municipality's own contribution €0.399 mil. and KfW grant €0.156 mil.
Role of Vodacom: Project Management and Consultant's partner
Consultant: DAHLEM, Beratende Ingenieure GmbH & Co. Wasserwirtschaft KG & Dr. Pecher AG
Contractor: Celtikcioglu, Turkey
Commencement date: August 2012
Implementation period: June 2020
Description:
  • Construction and reconstruction of the sewerage network – 20.3 km
  • Construction of 11 pumping stations
  • Construction of a sea outfall – 1.2 km
  • Construction and reconstruction of the water supply network – 10.2 km
Project results:

Systematic improvement of the water supply and sewage system, as well as enhancement of environmental conditions in the Bay of Kotor.

Water Supply and Sanitation Adriatic Coast – Herceg Novi
PHASE III (Immediate measures to improve the operation of the WWTP Herceg Novi)
Project status: Completed
Value: € 158,525.50 (final contract price)
Funding sources: KfW loan €0.159 mil.
Role of Vodacom: Project Management and Consultant's partner
Consultant: DAHLEM, Beratende Ingenieure GmbH & Co. Wasserwirtschaft KG & Dr. Pecher AG
Contractor: CMC Herceg Novi
Commencement date: August 2019
Implementation period: August 2019
Description:
  • Elimination of major issues on the drive shaft
  • Temperature probes
  • All pumps have been installed and successfully tested
  • Spare parts for the KSB pumps have been handed over to the Employer
  • The diesel generator has been successfully tested
  • The frequency inverter has been repaired and put back into operation
  • Mass flow meter: installation and calibration on the SBR tank successfully completed, and the signal forwarded to SCADA
  • Oil and air temperature sensors have been delivered and installed
  • Oxygen sensors
Project results:

Bringing the pumping system into operational condition and identifying operational issues within the WWTP system that could not be fully anticipated under the Contract, along with proposing further improvements to the system’s performance.

Water Supply and Sanitation Adriatic Coast – Herceg Novi
PHASE III (Immediate measures to improve the operation of the WWTP Herceg Novi)
Project status: Completed
Value: € 100,44.98 (final contract price)
Funding sources: KfW loan €0.100 mil.
Role of Vodacom: Project Management and Consultant's partner
Consultant: DAHLEM, Beratende Ingenieure GmbH & Co. Wasserwirtschaft KG & Dr. Pecher AG
Contractor: Biogest International, Drezden, Germany
Commencement date: May 2019
Implementation period: November 2019
Description:
  • Transport of 4 decanters
  • Dismantling of the existing 4 decanters
  • Testing of the new decanters
  • Training of the ViK staff for decanter installation
Project results:

Bringing the pumping system into operational condition and identifying operational issues within the WWTP system that could not be fully anticipated under the Contract, along with proposing further improvements to the system’s performance.