Bar

Implemented projects

Water Supply and Sanitation Adriatic Coast -Bar
PHASE III
Project status: Completed
Value: €10,846,026.01 (final Contract price)
Funding sources: KfW loan
Role of Vodacom: Project Management and Consultant's partner
Consultant: DAHLEM, Beratende Ingenieure GmbH & Co. Wasserwirtschaft KG & Dr. Pecher AG
Contractor: MPP Jedinstvo a.d. Sevojno - Uzice
Commencement date: November 2015
Implementation period: until October 2022 (for all sections under the Contract)
Description:
  • 5.8 km of water supply network
  • 19.2 km of sewage network
  • 1 km of stormwater network
  • 1 pumping station with the construction of the new “Sutomore” sea outfall
  • 1 reservoir “Susanj 2”
  • Construction of the water supply system for the settlement Sveti Ivan (Section 1 and Addendum 4)
  • Construction of the Volujica wastewater pumping station (Section 2.1 and Addendum 6)
  • Construction of the water supply system for the settlements Polje, Zaljevo, Sveti Ivan and Mala Volujica (Section 2.2 and Addendum 6), as well as
  • Construction of the extension of the water supply system for the settlement Zaljevo (Section 3 and Addendum 11)
Project results:

Systematic improvement of the water supply and wastewater disposal system and improvement of environmental conditions.